Agenda of the Twelfth KEKB Accelerator Review Committee

March 19-21, 2007
at Meeting room on the first floor of Build. No.3, KEK Tsukuba, Japan


KEKB Review Report (pdfdoc) (final:20070406) (Review Report Overview(JPN))

  Mar. 19 (Mon.)
  8:30- 9:00   Executive Session
  9:00- 9:10   Welcome   F. Takasaki   pdfppt
  9:10- 9:25   Overview   K. Oide   pdfkey
  9:25- 9:55   Beam Comissioning before Crab Cavity   Y. Funakoshi   pdfppt
  9:55-10:15   Belle Status   Y. Ushiroda   pdfppt
  10:15-10:35   Coffee    
  10:35-10:55   BPM Displacement Monitor   H. Fukuma   pdfppt
    ================ Crab Cavity ================
  10:55-11:30   Crab Cavity Overview   K. Hosoyama   pdfppt
  11:30-12:00   RF Design of Crab Cavity   Y. Morita   pdfppt
  12:00-13:00   Lunch    
  13:00-13:20   Cryogenics, etc.   K. Nakai   pdfppt
  13:20-13:45   Horizontal Tests for Crab Cavities   Y. Yamamoto   pdf
  13:45-14:05   Installation of Crab Cavity   M. Ono   pdfppt
  14:05-14:35   Commissioning of Crab RF System   K. Akai   pdfppt
  14:35-15:10   Beam Commissioning with Crab Cavity   H. Koiso   pdfppt
  15:10-15:30   Coffee    
  15:30-15:50   Beam-Beam Effect with Crab Cavity   K. Ohmi   pdfppt
  15:50-16:10   Observation of Crab Crossing with Streak Camera   H. Ikeda   pdfppt
    ============== Upgrade Studies ==============
  16:10-16:35   Recent Upgrade Studies of Vacuum Components   Y. Suetsugu   pdfppt
  16:35-16:50   Secondary Electron Yield   S. Kato   pdfppt
  16:50-17:05   Electron Cloud Measurement and Vacuum Chamber Design   K. Kanazawa   pdfppt
  17:05-17:20   Development of Pulsed Quadrupoles   T. Mimashi   pdfppt
  17:30-   Reception    
  Mar. 20 (Tue.)
  8:30- 9:00   Executive Session
  9:00- 9:20   QCS for SuperKEKB   N. Ohuchi   pdfppt
  9:20- 9:40   Crab Waist Optics   A. Morita   pdf
  9:40-10:00   Lattice Design for Super B   Y. Ohnishi   pdfppt
  10:00-10:20   Beam-Beam Effects in Super B   K. Ohmi   pdfppt
  10:20-10:40   Coffee    
  10:40-11:10   First application of a tungsten single-crystal positron source at the KEKB injector linac   T. Suwada   pdfppt
  11:10-11:40   Injector Upgrade   M. Satoh   pdfppt
  11:40-12:50   Lunch    
  12:50-13:20   Fuji Test Beam Line   J. Haba   pdfppt
  13:20-14:00   PEP-II Accelerator Status   J. Seeman   pdfppt
  14:00-15:00   Seminar: Design of Super B  (3G Seminar Hall)   P. Raimondi   pdfppt
    ================ Crab Tour ================
  15:00-15:30   Control Room with beam   H. Koiso  
  15:30-16:30   Nikko Tunnel without beam   K. Hosoyama  
  16:30-   Executive Session    
   
  Mar. 21 (Wed., Natl. Holiday)
  8:30- 11:00   Executive Session
  11:00- 12:00   Close-out with KEKB Staffs
  12:00   Adjourn
   



Review Committee Members